45 Asheland Moves Forward

May 24th, 2017

Progress continues on the 45 Asheland Condominiums. The project broke ground back in January of 2017, and as of May 23rd, 2017, the concrete podium is complete up to the second level. Concrete slabs are scheduled to be completed by the end of the month, and block work is slated to commence just after. Metal framing will begin in the first week of June. 45 Asheland is projected to be complete by Fall 2017.

Check out the pictures below to see how the project is coming along!